Available:*
Library | Item Barcode | Call Number | Material Type | Item Category 1 | Status |
---|---|---|---|---|---|
Searching... | 30000010127393 | HC79.C3 D44 2005 | Open Access Book | Book | Searching... |
On Order
Summary
Summary
Project and other structured finance models have become a method of choice for financing infrastructure projects in many different sectors across the globe. They allow greater flexibility for governments and project sponsors wishing to develop infrastructure without the concomitant burden on their balance sheets and their ability to fund other needs and priorities. However, The fall of Enron, WorldCom and so many other organisations who pushed the structured finance model one step too far has raised alarm bells. Has project and structured finance seen the end of its useful life? Are the risks surrounding such projects so extreme as to bring into question their usefulness? The viability of structured infrastructure projects relies on a comprehensive, yet sensible assessment of risk and allocation of that risk in an efficient manner. Yet our understanding of efficient risk allocation often runs contrary To The actual risk allocation models that we apply to such projects. Risk analysis for complex projects requires a level of sophistication and objectivity of which few individuals are capable. Jeff Delmon's book addresses the many issues around risk and structured infrastructure projects. it is not a dry legal treatise, but an eminently readable and practical explanation of efficient risk allocation And The contractual framework which forms the bedrock of BOT and other project finance transactions. Based on Jeff's practical experience in the sector, this book provides practical guidance and insight into many of the pitfalls often encountered in such projects. This book is ideal for those relatively new To The issues surrounding project finance and risk as well as those with significant experience as an aide-memoire and a challenge To The approaches to risk allocation that are so often applied to such transactions.
Table of Contents
Preface | p. xxvii |
Chapter 1 Risk, Risk Assessment and Risk Allocation | p. 1 |
1.1 Risk Assessment | p. 2 |
1.1.1 Quantitative risk assessment | p. 2 |
1.1.2 Qualitative risk assessment | p. 3 |
1.2 Quantitative Assessment | p. 4 |
1.2.1 Probability and standard mean variation | p. 5 |
1.2.2 Utility and cost-benefit analysis | p. 9 |
1.2.3 Causation | p. 12 |
1.2.4 Game theory | p. 12 |
1.2.5 Diversification | p. 13 |
1.2.6 Information | p. 14 |
1.3 Qualitative Assessment | p. 16 |
1.3.1 Basic needs | p. 17 |
1.3.2 Control and the search for certainty | p. 18 |
1.3.3 Magnitude | p. 23 |
1.3.4 Immediacy | p. 23 |
1.3.5 Focus | p. 23 |
1.3.6 Past personal experience/familiarity | p. 24 |
1.3.7 Physical condition and preparedness | p. 26 |
1.3.8 Personal, genetic or natural propensity to take risk | p. 27 |
1.3.9 Cultural | p. 28 |
1.3.10 Sociological | p. 29 |
1.3.11 Justice, equity and law | p. 29 |
1.3.12 Political context | p. 29 |
1.3.13 Power | p. 30 |
1.3.14 Institutional approaches or policy | p. 31 |
1.3.15 Team structure | p. 32 |
1.3.16 Education and training | p. 33 |
1.3.17 Technical | p. 33 |
1.3.18 Financial | p. 34 |
1.3.19 Commercial | p. 35 |
1.3.20 Risk Communication | p. 35 |
1.3.21 Nature versus nurture | p. 36 |
Chapter 2 Traditional Theory of Risk Allocation | p. 39 |
2.1 Elements of the Traditional Approach | p. 40 |
2.1.1 Who can control the occurrence of a risk? | p. 41 |
2.1.2 Who wants to be in a position of control over the circumstances related to the risk? | p. 42 |
2.1.3 Who can manage the risk for the least cost? | p. 42 |
2.1.4 Is the relevant party able to manage the risk, does it have the relevant resources and is it in a position to manage the risk? | p. 43 |
2.1.5 Can the relevant party bear the consequences of the risk? | p. 43 |
2.1.6 Is there an interrelationship between the relevant risk and other project risks? | p. 44 |
2.1.7 Will that party be motivated to manage the risk in the most efficient and effective manner possible? | p. 45 |
2.2 The Background to the Traditional Approach | p. 45 |
2.2.1 Latham, Egan, Grove and on | p. 45 |
2.2.2 Mechanisms to assist in implementing the traditional approach | p. 46 |
2.2.3 The traditional approach in other disciplines | p. 47 |
2.3 The Traditional Theory and Risk Noise | p. 47 |
2.3.1 Numeric quantification of linguistic quantitative assessment | p. 48 |
2.3.2 Hints at risk noise and its effects in the traditional approach literature | p. 49 |
2.4 Conclusion | p. 50 |
2.4.1 Political Drivers | p. 51 |
2.4.2 Finance Drivers | p. 52 |
2.4.3 Risk noise | p. 52 |
Chapter 3 Introduction to BOT Projects | p. 55 |
3.1 Private Investment in Public Infrastructure | p. 56 |
3.1.1 Public sector projects | p. 57 |
3.1.2 Financing | p. 58 |
3.1.3 Progression of financing | p. 59 |
3.1.4 Benefits and disadvantages | p. 59 |
3.2 Description of a BOT Project | p. 62 |
3.2.1 Financing agreement | p. 63 |
3.2.2 Shareholders' agreement | p. 64 |
3.2.3 Concession agreement | p. 64 |
3.2.4 Offtake purchase agreement | p. 64 |
3.2.5 Input supply agreement | p. 65 |
3.2.6 Construction contract | p. 65 |
3.2.7 Operation and maintenance agreement | p. 65 |
3.3 Direct Agreements | p. 65 |
3.4 Parties Involved in a BOT Project | p. 66 |
3.4.1 Lenders | p. 66 |
3.4.2 Grantor and host government | p. 67 |
3.4.3 Multilateral, bilateral and export credit agencies | p. 70 |
3.4.4 Project company | p. 72 |
3.4.5 Construction contractor | p. 73 |
3.4.6 Operator | p. 73 |
3.4.7 Offtake purchaser | p. 73 |
3.4.8 Input supplier | p. 74 |
3.4.9 Interfaces | p. 74 |
3.5 Stages of Development and Negotiation of a BOT Project | p. 75 |
Chapter 4 Project Finance | p. 79 |
4.1 Project Financing | p. 79 |
4.2 Types of Contributions | p. 83 |
4.2.1 Equity contributions | p. 83 |
4.2.2 Debt contributions | p. 83 |
4.2.3 Mezzanine contributions | p. 84 |
4.2.4 Debt-to-equity ratios | p. 85 |
4.3 Lender Recourse | p. 85 |
4.3.1 Recourse, limited recourse and non-recourse financing | p. 85 |
4.3.2 Rights against other persons | p. 87 |
4.3.3 Loss of non-recourse treatment | p. 87 |
4.4 Issues Specific to Financing Agreement | p. 88 |
4.4.1 Conditions precedent | p. 88 |
4.4.2 Security issues | p. 88 |
4.4.3 Repayment | p. 89 |
4.4.4 Shareholder support | p. 90 |
4.4.5 Step-in | p. 90 |
4.4.6 Warranties, undertakings and representations | p. 91 |
4.4.7 Use of insurance | p. 91 |
4.5 Other Issues Relevant to Financing | p. 92 |
4.5.1 Completion | p. 92 |
4.5.2 Host government support | p. 92 |
4.5.3 Force majeure and change in law | p. 93 |
4.5.4 Political risk | p. 94 |
4.5.5 Environmental risk | p. 94 |
4.5.6 Currency exchange risk | p. 94 |
4.5.7 Lenders' technical adviser | p. 95 |
4.5.8 Intercreditor issues | p. 95 |
Chapter 5 Project Bankability | p. 97 |
5.1 Project Viability | p. 98 |
5.1.1 Economic/political viability | p. 98 |
5.1.2 Legal viability | p. 100 |
5.1.3 Financial viability | p. 102 |
5.1.4 Technical viability | p. 103 |
5.2 Site Issues | p. 105 |
5.2.1 Political issues | p. 105 |
5.2.2 Administrative issues | p. 108 |
5.2.3 Currency issues | p. 110 |
5.2.4 Market issues | p. 110 |
5.2.5 Force majeure | p. 112 |
5.3 Source Country Issues | p. 112 |
5.4 Project Structure Issues | p. 112 |
5.4.1 Shareholders | p. 112 |
5.4.2 Financing structure | p. 113 |
5.4.3 Third party risk allocation | p. 114 |
5.5 Contractual Structure Issues | p. 115 |
5.5.1 Concession agreement | p. 115 |
5.5.2 Construction contract | p. 117 |
5.5.3 Operation and maintenance agreement | p. 119 |
5.5.4 Offtake purchase agreement | p. 120 |
5.5.5 Input supply agreement | p. 121 |
Chapter 6 Allocation of Risk in Project Finance | p. 125 |
6.1 Allocation of Risk | p. 126 |
6.2 Development Risk | p. 128 |
6.3 Completion Risk | p. 129 |
6.3.1 Construction | p. 129 |
6.3.2 Commissioning | p. 130 |
6.3.3 Time for completion | p. 131 |
6.4 Cost Increase Risk | p. 132 |
6.4.1 Currency risk | p. 132 |
6.4.2 Inflation | p. 133 |
6.4.3 Taxes | p. 133 |
6.4.4 Input price increase | p. 133 |
6.4.5 Construction cost increase | p. 134 |
6.4.6 Operation cost increase | p. 134 |
6.4.7 Cost of spare and replacement parts | p. 134 |
6.4.8 Decrease in output price | p. 135 |
6.4.9 Coverage of cost overrun risk | p. 135 |
6.5 Performance Risk | p. 136 |
6.5.1 Design and construction | p. 136 |
6.5.2 Operation | p. 137 |
6.5.3 Input supply | p. 137 |
6.5.4 Offtake purchaser infrastructure | p. 137 |
6.6 Operation Risk | p. 138 |
6.7 Market Risk | p. 139 |
6.7.1 Output price | p. 139 |
6.7.2 Input cost risk | p. 140 |
6.8 Political Risk | p. 140 |
6.8.1 Authority and enabling legislation | p. 140 |
6.8.2 Change in budget, government or political atmosphere | p. 140 |
6.8.3 Expropriations | p. 142 |
6.8.4 Change of law or taxation | p. 143 |
6.8.5 Change in technical requirements | p. 143 |
6.8.6 Immunities | p. 144 |
6.8.7 Public perception | p. 145 |
6.8.8 Political risk insurance | p. 146 |
6.8.9 Source country political risks | p. 147 |
6.8.10 Choice of law | p. 147 |
6.9 Environmental Risk | p. 148 |
6.10 Credit Risk | p. 150 |
Chapter 7 Project Participant Interface Risk | p. 153 |
7.1 Project Interfaces | p. 154 |
7.1.1 Technology interfaces | p. 154 |
7.1.2 Methodology interfaces | p. 154 |
7.1.3 Management and allocation of interface risk | p. 157 |
7.2 Grantor Interfaces | p. 157 |
7.2.1 Interfaces with construction contractor | p. 157 |
7.2.2 Interfaces with operator | p. 158 |
7.2.3 Interfaces with offtake purchaser | p. 159 |
7.2.4 Interfaces with input supplier | p. 160 |
7.3 Construction Contractor and Operator | p. 160 |
7.4 Operator and Offtake Purchaser | p. 162 |
7.5 Operator and Input Supplier | p. 163 |
7.6 Intra-project Company Interfaces | p. 163 |
Chapter 8 Concession Agreement | p. 165 |
8.1 Risks | p. 168 |
8.1.1 Political risk | p. 168 |
8.1.2 Completion risk | p. 169 |
8.1.3 Operation risk | p. 169 |
8.1.4 Permits and licences | p. 169 |
8.1.5 Transfer and re-tendering | p. 170 |
8.2 Interfaces | p. 170 |
8.2.1 Construction contractor | p. 170 |
8.2.2 Operator | p. 171 |
8.2.3 Offtake purchaser | p. 172 |
8.2.4 Input supplier | p. 172 |
8.3 Payment and Guarantees | p. 172 |
8.3.1 Tolls and tariffs | p. 172 |
8.3.2 Guarantees | p. 172 |
8.3.3 Non-competition/exclusivity | p. 173 |
8.3.4 Foreign currency exchange and transfer of funds | p. 173 |
8.3.5 Taxation | p. 173 |
8.3.6 Compensation events | p. 174 |
8.3.7 Compensation on termination | p. 174 |
8.4 Completion and Operation | p. 174 |
8.4.1 Design, construction and technical requirements | p. 174 |
8.4.2 Modification of technical requirements | p. 175 |
8.4.3 Time for completion and the project programme | p. 175 |
8.4.4 Method of operation | p. 176 |
8.4.5 Maintenance manuals, records and as-built drawings | p. 176 |
8.4.6 Update of project technology | p. 176 |
8.4.7 Training | p. 177 |
8.4.8 No discriminatory action by government or government entity | p. 177 |
8.5 Procedures and Mechanisms | p. 178 |
8.5.1 Approval, appointment and replacement | p. 178 |
8.5.2 Granting the concession | p. 178 |
8.5.3 Concession fees | p. 178 |
8.5.4 Independent expert | p. 178 |
8.5.5 Restrictions on transfer of shares of the project company | p. 179 |
8.5.6 Step-in and continuous operation provisions | p. 179 |
8.5.7 Transfer or re-tender | p. 179 |
Chapter 9 Shareholders' Agreement | p. 181 |
9.1 Form of the Project Company | p. 182 |
9.1.1 Added source of equity capital | p. 182 |
9.1.2 Special project expertise | p. 182 |
9.1.3 Shareholder interest | p. 183 |
9.1.4 Diversity of ownership | p. 183 |
9.1.5 Risk management | p. 183 |
9.1.6 Off balance sheet treatment | p. 183 |
9.1.7 Availability of funding | p. 184 |
9.1.8 Control over a resource or market position | p. 184 |
9.2 Investment, Return, Costs and Cash Flow | p. 184 |
9.2.1 Shareholder contributions | p. 184 |
9.2.2 New equity infusions | p. 185 |
9.2.3 Application of cash flow | p. 186 |
9.2.4 Costs | p. 186 |
9.2.5 Contribution clause | p. 186 |
9.3 Shareholder Rights and Obligations | p. 187 |
9.3.1 Shareholder undertakings | p. 187 |
9.3.2 Conflicts of interest | p. 187 |
9.3.3 Confidentiality | p. 188 |
9.3.4 Transfer to grantor | p. 188 |
9.3.5 Transfer of shares | p. 188 |
9.4 Management and Administration | p. 189 |
9.4.1 Management | p. 190 |
9.4.2 Dispute resolution | p. 190 |
Chapter 10 Construction Contract | p. 191 |
10.1 Turnkey Construction Contracts | p. 192 |
10.1.1 Single point responsibility | p. 193 |
10.1.2 Time for completion | p. 196 |
10.1.3 Fixed price | p. 197 |
10.1.4 Disadvantages | p. 198 |
10.2 Risk Allocation | p. 199 |
10.2.1 Completion risk | p. 199 |
10.2.2 Performance risk | p. 200 |
10.2.3 Increase of cost risk | p. 201 |
10.3 Interfaces between Construction Contractor and Other Project Participants | p. 201 |
10.3.1 Operator | p. 201 |
10.3.2 Offtake purchaser | p. 202 |
10.3.3 Input supplier | p. 203 |
10.4 Completion and Performance | p. 203 |
10.4.1 Scope of works | p. 203 |
10.4.2 Design | p. 204 |
10.4.3 Quality assurance | p. 204 |
10.4.4 Site risk | p. 205 |
10.4.5 Completion and takeover | p. 205 |
10.4.6 Tests on completion | p. 206 |
10.4.7 Performance tests | p. 207 |
10.4.8 Language | p. 207 |
10.5 Time | p. 207 |
10.5.1 Time for completion and project programme | p. 208 |
10.5.2 Late completion | p. 209 |
10.5.3 Defects liability period | p. 211 |
10.5.4 Latent defects | p. 211 |
10.6 Price and Payment | p. 212 |
10.6.1 Contract price | p. 212 |
10.6.2 Payment | p. 212 |
10.6.3 Bonds, guarantees and retention | p. 214 |
10.6.4 Limitation of liability | p. 215 |
10.6.5 Joint and several liability | p. 216 |
10.7 Additional Considerations | p. 216 |
10.7.1 Procurement restrictions | p. 216 |
10.7.2 Subcontracting | p. 216 |
10.7.3 Independent engineer | p. 217 |
10.7.4 Training and operation manuals | p. 217 |
10.7.5 Transfer of title and risk | p. 217 |
Chapter 11 Splitting Turnkey Construction Contracts | p. 219 |
11.1 Domestic Contracts | p. 220 |
11.2 International Contracts | p. 222 |
11.3 Splitting Contracts | p. 224 |
11.4 Setting the Terms | p. 225 |
11.5 Fixed Time for Completion | p. 225 |
11.5.1 Co-ordination of work programmes | p. 226 |
11.5.2 Testing and completion | p. 227 |
11.5.3 Timing of completion | p. 227 |
11.5.4 Liquidated damages for delay | p. 228 |
11.5.5 Duration of performance security | p. 231 |
11.6 Fixed Cost of Completion | p. 231 |
11.7 Single Point Responsibility | p. 232 |
11.7.1 Quality of the works | p. 233 |
11.7.2 Defects | p. 233 |
11.7.3 Interfaces between the contracts | p. 233 |
11.7.4 Dispute resolution | p. 234 |
11.7.5 Choice of law | p. 234 |
11.7.6 Limits of liability | p. 235 |
11.7.7 Insurance | p. 235 |
11.8 Splitting Terms | p. 235 |
11.8.1 Effective date | p. 236 |
11.8.2 Payment | p. 236 |
11.8.3 Cross-indemnities | p. 237 |
11.8.4 Termination | p. 237 |
11.8.5 Umbrella contracts | p. 238 |
11.9 Splitting the Works | p. 239 |
11.10 Conclusion | p. 240 |
Chapter 12 Operation and Maintenance Agreement | p. 241 |
12.1 Risk Allocation | p. 243 |
12.1.1 Performance risk | p. 243 |
12.1.2 Increase of cost risk | p. 244 |
12.1.3 Operation risk | p. 244 |
12.1.4 Political risk | p. 244 |
12.2 Interfaces | p. 245 |
12.2.1 Construction contractor | p. 245 |
12.2.2 Offtake purchaser | p. 247 |
12.2.3 Input supplier | p. 247 |
12.2.4 Grantor | p. 248 |
12.3 Operator's Obligations | p. 248 |
12.3.1 Scope of services | p. 248 |
12.3.2 Standards of performance | p. 249 |
12.3.3 Remedy of defects | p. 249 |
12.3.4 Emergency situations | p. 250 |
12.3.5 Procurement restrictions | p. 250 |
12.3.6 Spare parts | p. 250 |
12.3.7 Asset removal/replacement | p. 251 |
12.4 Payment | p. 251 |
12.4.1 Cost of operation and payment | p. 252 |
12.4.2 Budgeting for spare parts, major maintenance and asset renewal | p. 253 |
12.4.3 Operator as agent | p. 253 |
12.4.4 Liability | p. 254 |
12.4.5 Foreign exchange and convertibility | p. 254 |
12.5 Procedures | p. 254 |
12.5.1 Transfer of risk | p. 254 |
12.5.2 Independent engineer | p. 255 |
12.5.3 Access to books and records | p. 255 |
12.5.4 Training of the grantor's personnel | p. 255 |
12.5.5 Transfer | p. 256 |
Chapter 13 Offtake Purchase Agreement | p. 257 |
13.1 Risk Allocation | p. 259 |
13.1.1 Market risk | p. 260 |
13.1.2 Operation risk | p. 260 |
13.2 Interfaces | p. 260 |
13.2.1 Operator | p. 261 |
13.2.2 Construction contractor | p. 261 |
13.3 Primary Obligations | p. 261 |
13.3.1 Scope of services | p. 262 |
13.3.2 Quantity | p. 262 |
13.3.3 Technical and performance specifications | p. 262 |
13.3.4 Modifications to the project | p. 263 |
13.3.5 Facilities provided by offtake purchaser | p. 263 |
13.3.6 Ancillary services | p. 263 |
13.3.7 Completion and transition | p. 264 |
13.3.8 Transfer to grantor | p. 264 |
13.4 Price and Payment | p. 264 |
13.4.1 Capacity charge | p. 266 |
13.4.2 Usage charge | p. 267 |
13.4.3 Input efficiency | p. 268 |
13.4.4 Input supply | p. 268 |
13.4.5 Metering of output | p. 269 |
13.4.6 Other offtake | p. 269 |
13.4.7 Other pricing schemes | p. 270 |
13.4.8 Bonuses | p. 270 |
13.4.9 Guarantees | p. 270 |
13.4.10 Foreign exchange risk | p. 270 |
13.5 Mechanisms and Procedures | p. 271 |
13.5.1 Operation regime | p. 271 |
13.5.2 Maintenance regime | p. 271 |
Chapter 14 Input Supply Agreement | p. 273 |
14.1 Risk Allocation | p. 275 |
14.1.1 Market risk | p. 275 |
14.1.2 Operation risk | p. 275 |
14.2 Interfaces | p. 276 |
14.2.1 Operator | p. 276 |
14.2.2 Construction contractor | p. 276 |
14.3 Principal Obligations | p. 276 |
14.3.1 Quantity | p. 277 |
14.3.2 Procurement restrictions | p. 278 |
14.3.3 Source of input | p. 278 |
14.3.4 Shipment and storage | p. 280 |
14.3.5 Quality | p. 281 |
14.3.6 Completion and transition | p. 281 |
14.4 Payment | p. 282 |
14.4.1 Price | p. 282 |
14.4.2 Failure to deliver | p. 283 |
14.4.3 Testing quality | p. 284 |
14.4.4 Measuring quantity | p. 284 |
14.4.5 Payment | p. 284 |
14.4.6 Guarantees | p. 285 |
14.5 Mechanisms and Procedures | p. 285 |
14.5.1 Independent engineer | p. 285 |
14.5.2 Transfer to grantor | p. 285 |
Chapter 15 Issues Common to the Project Documents | p. 287 |
15.1 The Site | p. 287 |
15.1.1 Possession of and access to the site | p. 287 |
15.1.2 Site conditions | p. 289 |
15.2 The Works | p. 289 |
15.2.1 Procurement restrictions | p. 289 |
15.2.2 Transfer of title and risk | p. 290 |
15.2.3 Completion | p. 291 |
15.2.4 Spare parts | p. 292 |
15.3 Payment | p. 292 |
15.3.1 Price, payment and revenues | p. 292 |
15.3.2 Foreign currency exchange | p. 293 |
15.3.3 Guarantees | p. 294 |
15.4 Changes | p. 294 |
15.4.1 Assignment | p. 295 |
15.4.2 Change in law | p. 295 |
15.4.3 Change in pricing mechanism | p. 296 |
15.4.4 Change in requirements | p. 296 |
15.4.5 Dispute | p. 296 |
15.4.6 Lenders' interests | p. 296 |
15.5 Political and Natural Events | p. 297 |
15.5.1 Licences and permits | p. 297 |
15.5.2 Force majeure | p. 299 |
15.5.3 Sovereign immunity | p. 301 |
15.5.4 Types of insurance | p. 302 |
15.5.5 Insurance issues | p. 305 |
15.6 Termination and Step-in | p. 307 |
15.6.1 Termination | p. 307 |
15.6.2 Step-in and continuous operation provisions | p. 308 |
15.6.3 Transfer to grantor | p. 309 |
15.7 Supervision and Disputes | p. 310 |
15.7.1 Grantor/lender access and inspection | p. 310 |
15.7.2 Independent engineer | p. 311 |
15.7.3 Dispute resolution | p. 311 |
15.8 Miscellaneous | p. 313 |
15.8.1 Definitions | p. 313 |
15.8.2 Conditions precedent | p. 313 |
15.8.3 Duration | p. 314 |
15.8.4 Language | p. 315 |
15.8.5 Confidentiality | p. 315 |
15.8.6 Training | p. 316 |
15.8.7 Choice of law | p. 316 |
15.8.8 Schedules | p. 317 |
15.9 Direct Agreements | p. 318 |
Chapter 16 Tendering Procedures | p. 321 |
16.1 The Procedures | p. 322 |
16.1.1 Pre-qualification | p. 323 |
16.1.2 Tender documentation | p. 324 |
16.1.3 Bid evaluation | p. 326 |
16.1.4 Preferred bidder | p. 326 |
16.2 The Purpose | p. 326 |
16.2.1 Efficiency | p. 327 |
16.2.2 Competition | p. 327 |
16.2.3 Transparency | p. 328 |
16.3 The Approaches | p. 329 |
16.3.1 Bidder response | p. 329 |
16.3.2 Fixed approach | p. 331 |
16.3.3 Negotiated approach | p. 333 |
16.4 Project Finance and Involving the Financiers | p. 335 |
16.4.1 Bankability | p. 336 |
16.4.2 Introduction of the financiers post-bid | p. 336 |
16.4.3 Introduction of the financiers pre-bid | p. 337 |
16.4.4 Managing financiers | p. 337 |
16.5 Solutions to Efficient Tendering | p. 338 |
16.5.1 Availability of resources to the grantor | p. 339 |
16.5.2 Reducing terms | p. 340 |
16.5.3 Variant bids | p. 342 |
16.5.4 Reducing numbers | p. 343 |
16.5.5 Three-stage bidding | p. 344 |
16.5.6 Consolidation of technical information | p. 345 |
Chapter 17 Power Projects | p. 347 |
17.1 BOT to BOO | p. 348 |
17.2 Merchant Power | p. 348 |
17.3 Merchant Power in the United States | p. 349 |
17.4 Tolling Agreements | p. 350 |
17.5 Grid Requirements | p. 350 |
17.6 Currency Mismatch | p. 351 |
17.7 New Electricity Trading Arrangements | p. 352 |
17.8 Other Offtake | p. 353 |
17.9 Special Characteristics | p. 354 |
17.9.1 Black start | p. 354 |
17.9.2 Reactive power | p. 355 |
17.9.3 Frequency responsive generation | p. 355 |
17.9.4 Load shedding | p. 355 |
17.10 Fuel | p. 355 |
17.11 Nuclear Fuel | p. 356 |
17.12 Renewables | p. 356 |
17.12.1 The drive for renewable energy sources | p. 357 |
17.12.2 Other available solutions | p. 358 |
17.12.3 Government incentives | p. 358 |
17.12.4 Wind projects | p. 360 |
17.13 Energy from Waste | p. 363 |
17.13.1 The call for energy from waste | p. 363 |
17.13.2 Project issues | p. 364 |
Chapter 18 Transportation | p. 369 |
18.1 Roads and Bridges | p. 369 |
18.1.1 Operating costs | p. 370 |
18.1.2 Revenues | p. 370 |
18.1.3 Existing facilities | p. 371 |
18.1.4 Land and environmental risks | p. 371 |
18.2 Railways | p. 372 |
18.2.1 Revenues | p. 372 |
18.2.2 Interface with existing facilities | p. 373 |
18.2.3 Land and the environment | p. 373 |
18.2.4 Capital cost and subsidies | p. 374 |
18.2.5 Forecasts | p. 374 |
18.2.6 Extension or refurbishment of existing railways | p. 375 |
18.2.7 Regulation and safety | p. 376 |
18.2.8 BOT and DBT models | p. 376 |
18.3 Airports | p. 377 |
18.3.1 Revenue | p. 377 |
18.3.2 Regulation | p. 378 |
18.3.3 Design and long-term planning | p. 379 |
18.3.4 Land and environment | p. 380 |
18.3.5 Financing | p. 380 |
18.3.6 Traffic forecasts | p. 381 |
Chapter 19 Oil and Gas | p. 383 |
19.1 Oil and Gas Projects | p. 384 |
19.1.1 Oil and gas industries | p. 384 |
19.1.2 Operational issues | p. 385 |
19.2 Extractive Projects | p. 385 |
19.2.1 Regulation | p. 386 |
19.2.2 Reserves | p. 386 |
19.2.3 Oil and gas rights | p. 387 |
19.2.4 Commercial arrangements and equipment | p. 387 |
19.2.5 Credit risk and security | p. 388 |
19.2.6 Market liquidity | p. 389 |
19.2.7 Investment structures | p. 389 |
19.3 Pipelines to Refineries | p. 391 |
19.3.1 Revenues | p. 391 |
19.3.2 Political/cross-border issues | p. 391 |
19.4 Gas and LNG | p. 392 |
19.4.1 The LNG chain | p. 394 |
19.4.2 Revenues | p. 394 |
19.4.3 Transport | p. 395 |
19.4.4 Regulation | p. 396 |
19.4.5 Taxation and the project structure | p. 396 |
19.4.6 The future of LNG | p. 397 |
Chapter 20 Telecommunications | p. 399 |
20.1 Telecommunications | p. 399 |
20.1.1 Market risk | p. 400 |
20.1.2 Technology | p. 401 |
20.1.3 Regulation | p. 402 |
20.2 Fibre Optic Projects | p. 402 |
20.2.1 What is a fibre network? | p. 403 |
20.2.2 Property | p. 404 |
20.2.3 Construction contracts | p. 405 |
20.2.4 Operation issues | p. 407 |
20.2.5 Offtake contracts | p. 408 |
20.2.6 Lenders' security | p. 409 |
Chapter 21 Water and Sanitation | p. 411 |
21.1 Structures for Private Sector Participation in Water Projects | p. 413 |
21.1.1 Management contracts | p. 414 |
21.1.2 BOT projects | p. 415 |
21.1.3 Concessions | p. 416 |
21.1.4 Share or asset sale privatisation | p. 417 |
21.2 Water Projects, BOTs and Concessions | p. 418 |
21.2.1 Why water projects often require concessions | p. 418 |
21.2.2 Problems with concessions | p. 420 |
21.2.3 Challenges in financing concessions | p. 422 |
21.3 Water and Sewage Treatment | p. 424 |
21.3.1 Sewage treatment | p. 424 |
21.3.2 Water treatment | p. 426 |
Chapter 22 Outsourcing | p. 431 |
22.1 Risk Allocation | p. 432 |
22.2 Governance | p. 432 |
22.3 Exclusivity | p. 433 |
22.4 Scope of Services | p. 434 |
22.4.1 Nature of services | p. 434 |
22.4.2 Nature of provision of services | p. 435 |
22.5 Service Levels | p. 436 |
22.6 Change of Requirements and Additional Services | p. 438 |
22.7 Compensation | p. 438 |
22.8 Grantor Obligations | p. 439 |
22.9 Benchmarking | p. 439 |
22.10 Intellectual Property Rights | p. 440 |
22.11 Employees | p. 440 |
22.12 Legal and Regulatory Compliance | p. 441 |
22.13 Termination | p. 442 |
22.14 Joint Venture Arrangements | p. 442 |
22.15 Multi-jurisdictional Arrangements | p. 443 |
22.16 Offshore Outsourcing | p. 444 |
Glossary | p. 447 |
Index | p. 513 |